Tuesday, April 28, 2015

April 28, 2015

 Doors and windows are installed, sidewalks are poured, interior is insulated, grey coat on the stucco is done – guess it has to dry for a week, then they do the color coat, roof is done.  We’re waiting for the inspector to sign off on the insulation so that they can begin to dry wall.  J.R. moved the flooring in this afternoon so it can be acclimating while they finish out the rest of the interior.  Plumber and electrician have been waiting for the contractor to catch up to them so that they can proceed.  Probably won’t be done as soon as I was hoping, but it is progressing.